Friday, November 30, 2012

end of framing stage...





Monday, November 26, 2012

We had quite a severe thunderstorm last night and this morning, so I went up to check on the site today. Typical Melbourne weather - by the time I got 7kms from Gisborne it was sunny, 22 degrees.

Drove past the site - there were workman there. We're not really supposed to turn up unannounced, so I didn't disturb them. Property looked fine. Pheeeeew!

They're doing the roof trusses! So we look to be on track to finish the framing stage end of this week (if there's no more rain). 

Friday, November 23, 2012

It's a house...almost



From the road into Gisborne

Zoomed out...from the same road

The house!



The windows...on the ground!?


Friday, November 16, 2012

The slab is down

The driveway and garage

 Standing at the front porch looking through the main hallway

more front porch...
The junction box....exciting!

The driveway to garage....we're thinking of keeping the aggregate they have put down. Beats spending thousands on a driveway!

Saturday, November 3, 2012

They've broken ground

Went up there last weekend to find a large amount of earth moved in prep for the slab. Finished off the mowing before they put the fence up to stop kids getting in.

Photos of...



We went there yesterday, and the fence was up. Didn't take a photo...really, its only a fence.